SOLUTION: The amount A paid to a work crew varies jointly as the number of persons working N and the length of time worked t. If 5 bricklayers take 6 days to finish a certain job, how long w
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: The amount A paid to a work crew varies jointly as the number of persons working N and the length of time worked t. If 5 bricklayers take 6 days to finish a certain job, how long w
Log On
Question 959586: The amount A paid to a work crew varies jointly as the number of persons working N and the length of time worked t. If 5 bricklayers take 6 days to finish a certain job, how long would it take 7 bricklayers to finish a similar job requiring 4 times the number of bricks?
Round your answer to the nearest integer.
You can put this solution on YOUR website! You can say:
5 bricklayers take 6 days to do 1 job
-----------------------------------
If another job requires 4 times the number of bricks
you can say that is 4 jobs, so
7 bricklayers take days to finish 4 jobs
------------------------------------------
7 times as many bricklayers can do 1 job in 1/7 the time, so
35 bricklayers take 6/7 days to do 1 job
-----------------------------------------
1/5 as many bricklayers will take 5 times as long, so
7 bricklayers take 30/7 days to do 1 job
--------------------------------------
4 jobs will take 4 times as long, so
7 bricklayers take 120/7 days to do 4 jobs
------------------------------------- , so
7 bricklayers take 17 and 1/7 days to do 4 jobs
------------------
Hope I got it