SOLUTION: 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.

Algebra ->  Rate-of-work-word-problems -> SOLUTION: 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.       Log On


   



Question 956605: 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.
Answer by lwsshak3(11628) About Me  (Show Source):
You can put this solution on YOUR website!
70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.
***
man-days required to dig 15000 sq m field=5*70=350
man-days required to dig 22500 sq m field=225/150*5/25*350=105
men required=105/25=4.2