Question 955333: 12 workers take 18 days to renovate a house. After working for 3 days, 4 workers left. Calculate the number of days the remaining workers will need to complete the renovation Found 2 solutions by Fombitz, MathTherapy:Answer by Fombitz(32388) (Show Source):
You can put this solution on YOUR website! Rate x Time= Output
So the rate for one worker is,
.
.
.
For 12 workers working 4 days, their output is,
The amount needed to complete the job is,
Now there are only 8 workers so,
You can put this solution on YOUR website!
12 workers take 18 days to renovate a house. After working for 3 days, 4 workers left. Calculate the number of days the remaining workers will need to complete the renovation
Time taken to complete of remaining renovation by 8 (12 - 4) workers: hours