SOLUTION: it takes 8 men 9 hours to dig a trench.how long would it take 6 men to dig the trench if they worked at the same rate?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: it takes 8 men 9 hours to dig a trench.how long would it take 6 men to dig the trench if they worked at the same rate?       Log On


   



Question 953867: it takes 8 men 9 hours to dig a trench.how long would it take 6 men to dig the trench if they worked at the same rate?

Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
it takes 8 men 9 hours to dig a trench.
Find the number of man-hrs required to dig the trench
8 * 9 = 72 man-hrs
:
how long would it take 6 men to dig the trench if they worked at the same rate?
let t = time required by 6 men
6t = 72
t = 72/6
t = 12 hrs to do the job with 6 men