SOLUTION: A painting project will take a total of 360 person days to complete. How many days will it take to complete the project if 30 people work on the project? If the project must be co
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A painting project will take a total of 360 person days to complete. How many days will it take to complete the project if 30 people work on the project? If the project must be co
Log On
Question 950908: A painting project will take a total of 360 person days to complete. How many days will it take to complete the project if 30 people work on the project? If the project must be completed in 10 days how many people must be employed? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! person-days is equal to: person-days
It will take days if
people work on the project
-------------------------- people must be employed
to finish in days