SOLUTION: A painting job can be completed by 3 painters in 17 days. If 12 more painters join the team 2 days after starting work on the job, then how many more days are required to complete
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A painting job can be completed by 3 painters in 17 days. If 12 more painters join the team 2 days after starting work on the job, then how many more days are required to complete
Log On
Question 947264: A painting job can be completed by 3 painters in 17 days. If 12 more painters join the team 2 days after starting work on the job, then how many more days are required to complete the job? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! What fraction of the job can the painters
get done in days?
They can do of the job
That leaves of the job left to do
----------------------------------------
It is assumed ( but they don't say it ) that the
extra painters work at the same rate as
the first
-------------------
There are painters total after
the 1st 2 days
------------------- times as many painters can work at times the rate, so their rate is
( 1 job ) / ( 17/5 days ) =
Now I can say: ( t is time in days )
Multiply both sides by
3 days are required to finish the job
hope I got it