Question 942521
:
If 210 men can complete a piece of work in 44 days. How many days will 280 men take to do it?
It should be done in unitary method.
Answer by
josgarithmetic(39630)
(
Show Source
):
You can
put this solution on YOUR website!
What is the "unitary method"?
Let r be the rate for one man, units of PIECE per DAYS.
RT=J rate time piece of work.
and
.
The "1" is for "one piece of work".
Take it from there.