2 men take 12 days to build a bridge, how many days does it take for 1 man?
Answer by
macston(5194)
(
Show Source
):
You can
put this solution on YOUR website!
2 men x 12 days=24 man days
24 man days/1 man=24 days It takes one man 24 days to build the bridge