Question 941375: If 8 men took 10 days to complete a job. And 3 men fell ill on the six day. How much longer would it take to complete the job putting into consideration the men worked evenly
You can put this solution on YOUR website! If 8 men took 10 days to complete a job. And 3 men fell ill on the six day.
How much longer would it take to complete the job putting into consideration the men worked evenly
:
Find how many man-days required to do the job.
8 * 10 = 80 man-days
:
When three men call in sick on the 6th day. (completed 5 days of work)
8 men worked for five days,
5 remaining men take d days to complete the job
(8 * 5) + 5d = 80
40 + 5d = 80
5d = 80 - 40
5d = 40
d = 40/5
d = 8 more days