SOLUTION: If 54 men working 10 hours a day can finish a work job in 15 days, how many men are needed to complete the same job in 18 days while only working 9 hours a day? _______men
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: If 54 men working 10 hours a day can finish a work job in 15 days, how many men are needed to complete the same job in 18 days while only working 9 hours a day? _______men
Log On
Question 931625: If 54 men working 10 hours a day can finish a work job in 15 days, how many men are needed to complete the same job in 18 days while only working 9 hours a day? _______men Answer by Alan3354(69443) (Show Source):
You can put this solution on YOUR website! If 54 men working 10 hours a day can finish a work job in 15 days, how many men are needed to complete the same job in 18 days while only working 9 hours a day?
--------------
10 hr/day * 15 days = 150 hours
54*150 = 8100 man-hrs for the job.
-----------
Can you finish it?