SOLUTION: A water tank which takes 2 hours in getting filled normally, It is taking 20 minutes extra in getting filled fully since it has leakage problem.
How much time it will take in ge
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A water tank which takes 2 hours in getting filled normally, It is taking 20 minutes extra in getting filled fully since it has leakage problem.
How much time it will take in ge
Log On
Question 921959: A water tank which takes 2 hours in getting filled normally, It is taking 20 minutes extra in getting filled fully since it has leakage problem.
How much time it will take in getting vacant fully ? Answer by josgarithmetic(39800) (Show Source):
You can put this solution on YOUR website! x, time for leak to empty the tank. hour is same as 20 minutes.
Basic rule for uniform rates for a job, task, or a measure of a continuous process that has measurable quantity is RT=Q for rate, time, quantity.