SOLUTION: A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional men be employed,
Question 910701: A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional men be employed, so that the work may be completed in time if each man works 9 hours a day? Answer by josgarithmetic(39614) (Show Source):
You can put this solution on YOUR website! Use the data for what was done to find the one-man work rate per hour. The needed additional men would need to work for to do of the job.
That is not the solution; but is only guidance on strategy for a solution.
A START FOR THE SOLUTION PROCESS:
r is the one-man rate of work, jobs per HOUR. .
Rate was 104*r, and the number of HOURS was .
Find r. , the one-man rate in JOBS per HOUR. That is 1 job in 65000 days, for just ONE man.
The remaining amount of job to be done will use n additional men and will require days at 9 hours per day.
... That's the idea.
FINISHING THE PROCESS:
because of the job was already done.
theoretically, , but realistically, the number of workers added should be .