Question 906584: 540 men can construct a building in 7 months, how many men should removed from work to finish the building in 9 months?

Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
540*7=3780 worker months
540-420=120 to be removed
420*9=3780