SOLUTION: 540 men can construct a building in 7 months, how many men should removed from work to finish the building in 9 months?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: 540 men can construct a building in 7 months, how many men should removed from work to finish the building in 9 months?