SOLUTION: it takes 12 workers 10 days to complete a piece of roadway how long will it take 5 workers to do the same tasks?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: it takes 12 workers 10 days to complete a piece of roadway how long will it take 5 workers to do the same tasks?