SOLUTION: If 3 men can complete three tasks in 3 hours,how many men will complete 24 tasks in 6 hours?
Algebra
->
Rate-of-work-word-problems
-> SOLUTION: If 3 men can complete three tasks in 3 hours,how many men will complete 24 tasks in 6 hours?
Log On
Word Problems: Rate of work, PAINTING, Pool Filling
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Rate-of-work-word-problems
Question 906369
:
If 3 men can complete three tasks in 3 hours,how many men will complete 24 tasks in 6 hours?
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
3*3=9
9/3=3 hours per man per task
1 man can complete 2 tasks in 6 hours
12 men can complete 24 tasks in 6 hours