SOLUTION: printing machine A can do printing in 8 hours. With the machine B the same printing would take 12 hours. It was decided that both machines will be used for the printing. However, a
Algebra ->
Customizable Word Problem Solvers
-> Misc
-> SOLUTION: printing machine A can do printing in 8 hours. With the machine B the same printing would take 12 hours. It was decided that both machines will be used for the printing. However, a
Log On
Question 905924: printing machine A can do printing in 8 hours. With the machine B the same printing would take 12 hours. It was decided that both machines will be used for the printing. However, after a while the machine A broke down. After that it took 6 hours to finish the printing with machine B. How many hours did the machine A print before it broke down? Answer by josgarithmetic(39614) (Show Source):