SOLUTION: If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days , then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys

Algebra ->  Rate-of-work-word-problems -> SOLUTION: If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days , then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys      Log On


   



Question 903499: If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days , then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys
Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days ,
Find how many man-hrs to make 12 toys
12*9*6 = 648 man-hrs
then find how many man-hrs to make one toy
648/12 = 54 man-hrs per toy
:
then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys
let d = no. of days required to accomplish this
18*6*d = 24*54
108d = 1296
d = 1296/108
d = 12 days