SOLUTION: If 3 people who work at the same rate can paint a house in 8 days, what fractional part of the house can one person paint in 2 days?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: If 3 people who work at the same rate can paint a house in 8 days, what fractional part of the house can one person paint in 2 days?
Log On
Question 903261: If 3 people who work at the same rate can paint a house in 8 days, what fractional part of the house can one person paint in 2 days? Answer by josgarithmetic(39630) (Show Source):