SOLUTION: Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work together for 6 days and then A leaves. How long will B take to finish the work ?
Algebra ->
Customizable Word Problem Solvers
-> Misc
-> SOLUTION: Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work together for 6 days and then A leaves. How long will B take to finish the work ?
Log On
Question 900266: Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work together for 6 days and then A leaves. How long will B take to finish the work ? Answer by richwmiller(17219) (Show Source):
You can put this solution on YOUR website! 1/a+1/b=1/x
1/20+1/b=1/15
3/20+1/b=4/60
1/b=1/60
b=60
check
1/20+1/60=1/15
3/60+1/60=4/60
4/60=4/60
ok
6/20+6/60+x/60=1
18/60+6/60+x/60=1
24/60+x/60=1
x/60=36/60=6/10
A and B did 24/60=.4 together
x=36 days for B to finish .6 of the job alone