SOLUTION: 25 workers can complete a work in 30 hours find the no. of hours required to complete same work by 10 workers

Algebra ->  Rate-of-work-word-problems -> SOLUTION: 25 workers can complete a work in 30 hours find the no. of hours required to complete same work by 10 workers      Log On


   



Question 895790: 25 workers can complete a work in 30 hours find the no. of hours required to complete same work by 10 workers
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
I wrote your question in English. you copied and pasted it wrong.
25*30=750 man hours
750/10=75 hours for 10 workers