SOLUTION: three men do a job in 12 days.Two of the men work twice ass fast as third.How long will it take one of the faster men.

Algebra ->  Rate-of-work-word-problems -> SOLUTION: three men do a job in 12 days.Two of the men work twice ass fast as third.How long will it take one of the faster men.      Log On


   



Question 894263: three men do a job in 12 days.Two of the men work twice ass fast as third.How long will it take one of the faster men.
Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
three men do a job in 12 days.
Two of the men work twice as fast as third.
How long will it take one of the faster men.
:
let t = time required by one of the faster men to do the job alone
then
2t = time required by the slower guy
:
Let the completed job = 1
:
A shared work equation
12%2Ft + 12%2Ft + 12%2F%282t%29 = 1
multiply thru by 2t
2(12) + 2(12) + 12 = 2t
24 + 24 + 12 = 2t
60 = 2t
t - 60/2
t = 30 days for one of the faster guys to do the job
:
:
you can check this for yourself
12%2F30 + 12%2F30 + 12%2F%2860%29 =