Question 892082: A can do a piece of work in 16 days. After working on it for 4 days B joins who can complete work in 32 days. if A earns 1200 how much does B earn ?
Answer by josgarithmetic(39623) (Show Source):
You can put this solution on YOUR website! No clue how pay rate is related between A and B or to the work. Maybe just assumption of equal pay per time.
Are they paid at the same hourly rate?
WORK RATES:
A, 
B, 
A&B,
They complete 1 job in a combination of persons and days.
A for 4 days and then A&B for 32 days.
RT=J, for rate, time, job.
Solve this equation for x. The time for B to do the 1 job alone would be x days.
When you know x, you can find the work rate for B and the work rate of A and B combined.
THE ACTUAL QUESTION ASKED:
Your question was about pay rate and how much money B received. If both A and B get the same
daily rate of pay, then The pay rate for either of them is doller per day, based on the time and moneys
that A worked and received.
ANSWER:_____B worked for 32 days (while working together with A). B would earn 
Apparently, solving for the time for B to do 1 job alone is not needed for finding how much he earns
in his 32 days of work.
|
|
|
| |