SOLUTION: If 10 workers do a certain work in 16 days, than in how many days the same work will be done by 32 workers?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: If 10 workers do a certain work in 16 days, than in how many days the same work will be done by 32 workers?      Log On


   



Question 891799: If 10 workers do a certain work in 16 days, than in how many days the same work will be done by 32 workers?
Answer by josgarithmetic(39613) About Me  (Show Source):
You can put this solution on YOUR website!
r = rate for 1 worker.
d = days of work for the 32 workers.
RT=J, rate time job, uniform rate equation for doing work or a task or a job.
Rate for any n workers at the same time is n%2Ar.

Each part of the description is for 1 whole job.
highlight%2810%2Ar%2A16=1=32%2Ar%2Ad%29