Question 889281
:
Considering 4 men finishes the work in 2 days, how many men will require to finish the work in half day?
Found 2 solutions by
josgarithmetic, richwmiller
:
Answer by
josgarithmetic(39628)
(
Show Source
):
You can
put this solution on YOUR website!
r = rate of 1 man per day
n = count of men to do the job in half a day
RT=J for rate, time, job.
Each man assumed works at same rate as another man. Rate of a group of men is the sum of the rate of the men in the group
Solve for n.
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
8 man days to finish the job
16 men will finish it in 1/2 day