Question 885169: A job can be done by 25 men in 32 days. After 8 days, 5 men left. how long will it take the remaining men to finish the job?
Found 3 solutions by AnlytcPhil, richwmiller, MathTherapy: Answer by AnlytcPhil(1806) (Show Source): Answer by richwmiller(17219) (Show Source):
You can put this solution on YOUR website! 25*32=800
it takes 800 man days to finish the job
8*25=200
in 8 days they used 200 man days
800-200=600
so they need 600 more man days to finish the job.
600/20=30 more days to finish the job
checking out reasonableness.
if the 25 continued they would take 24 more days so it is reasonable that it would take 20 men 30 days to finish
Answer by MathTherapy(10552) (Show Source):
You can put this solution on YOUR website!
A job can be done by 25 men in 32 days. After 8 days, 5 men left. how long will it take the remaining men to finish the job?
It'll take the remaining 20 men, days to complete the remaining of the job
You can do the check!!
If you need a complete and detailed solution, let me know!!
Send comments, “thank-yous,” and inquiries to “D” at MathMadEzy@aol.com.
Further help is available, online or in-person, for a fee, obviously.
For FREE info and answers to questions about the ASVAB exam, the NYS 3 – 8 city/state wide exams,GENERAL
MATH and HOMEWORK QUESTIONS, or MATH QUESTIONS related to the Regents Integrated Algebra,
Regents Geometry, Regents Algebra 2/Trigonometry, SHSAT, COOP/HSPT/TACHS, PSAT, SAT, ACT, SSAT/ISEE,
GRE, CLEP, and the TASC/GED, you can visit: http://asvabstudyzone.freeforums.net/.
|
|
|
| |