SOLUTION: two men A and B can finish a work in 16 days and 12 days respectively.A and B are working together after 4 days A left the work,then the remaining work completed by B in how many d
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: two men A and B can finish a work in 16 days and 12 days respectively.A and B are working together after 4 days A left the work,then the remaining work completed by B in how many d
Log On
Question 883377: two men A and B can finish a work in 16 days and 12 days respectively.A and B are working together after 4 days A left the work,then the remaining work completed by B in how many days? Answer by Edwin McCravy(20056) (Show Source):
You can put this solution on YOUR website! two men A and B can finish a work in 16 days and 12 days respectively.A and B are working together after 4 days A left the work,then the remaining work completed by B in how many days?
>>A...can finish a work in 16 days<<
So A's rate is
>>...B can finish a work in...12 days<<
So B's rate is
A and B are working together...(for)...4 days
So their combined work rate is
For those 4 days before A left, they had done
So, when A left, there was still of the job left for B to do by
himself. Suppose it took B alone N days to do the remaining of the
job. Since B's work rate is , the equation is:
or
Multiply both sides by LCD=12
N = 5 days.
Edwin