Question 878918: A can do a piece of work in 9 days while B can do the work in 15 days. Both began the work together. After how many days should A leave so the total time taken for the job is 10 days.
A) 3
B) 4
C) 6
D) 8 Answer by josgarithmetic(39617) (Show Source):
A, 1/9 jobs per day;
B, 1/15 jobs per day.
If A and B work at the same time, rate is jobs per day.
If working together and then A leaves, then remaining time is worked by B.
A and B work together for x days, and then B continues to work alone for y days. AND .
The arithmetic and number property solving steps are undone so you can do them.