Question 877337
:
if a man can sew 120 pants in 5 days how long will it take 15 men to sew 120 pants?
Answer by
josmiceli(19441)
(
Show Source
):
You can
put this solution on YOUR website!
15 men can do it in 1/15 of the time
that 1 man takes, so
15 men sew 120 pants in 5/15 = 1/3
of a day