SOLUTION: It takes 6 men 4 days to build 3 houses. How many days do 10 men take to build 7 houses?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: It takes 6 men 4 days to build 3 houses. How many days do 10 men take to build 7 houses?      Log On


   



Question 870028: It takes 6 men 4 days to build 3 houses.
How many days do 10 men take to build 7 houses?

Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
6*4=24 man days
24/3=8 man days per house
7*8=56 man days for 7 houses
56/10 =5.6 days for 10 men to build 7 houses