Question 870028
:
It takes 6 men 4 days to build 3 houses.
How many days do 10 men take to build 7 houses?
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
6*4=24 man days
24/3=8 man days per house
7*8=56 man days for 7 houses
56/10 =5.6 days for 10 men to build 7 houses