Question 862083: A building contractor is to dig a foundation 45 feet long, 25 feet wide, and 9 feet deep. The contractor pays $11 per load for trucks to remove the dirt. Each truckload holds 5 cubic yards. What is the cost to the contractor to have all the dirt hauled away?
You can put this solution on YOUR website! 45 feet long, 25 feet wide, and 9 feet deep.
convert to yards
45/3 , 25/3 9/3
Volume = 15*(25/3)*3
375 cu yards
5 cu yards / load
375/5 = 75 loads
$ 11 per load
75 * 11= $825