Question 853815: Hi I really need help with these questions please. Could someone show their solution too please. Thank you so much.
1.)It takes 5 people 6 days to complete a task, sharing the work evenly.
a.) how long will it take 6 people to complete the task?
b.) If the task is to be completed in two days how many people are required?

Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
a) 5*6=30 people days 30/6=5 days for 6 people
a) 30/2=15 days for 2 people