Question 85254:  Hi, 
 
 
I need help with this word problem:
 
 
A factory has an order for 23,500 paper clips. Machine A can make 1500 paper clips per hour while Machine B can make 2500 paper clips per hour. Machine A starts at 8:00am and Machine B starts work at 1:00pm. At what time will the two machines complete the job?
 
 
Thank you!!! 
 Answer by ptaylor(2198)      (Show Source): 
You can  put this solution on YOUR website!  
When Machine B starts at 1:00pm, Machine A has already made 5*(1500) or 7500 paper clips.  So when the two machines start working together at 1:00pm, there are 23,500-7500 or 16,000 paper clips yet to be made. Together, the machines can make 1500+2500 or 4000 paper clips per hour.  So, in 16,000/4000 or 4 hours, they can finish the job and that would be 1:00pm plus 4 hours =5:00pm
 
Let x=amount of time it takes both machines to do the job after they both start working together at 1:00pm
 
So our equation to solve is:
 
1500*5+4000*x=27,500 or 
7500+4000x=27,500 subtract 7500 from both sides
 
4000x=16000  divide both sides by 4000 
x=4 hrs
 
1:00pm+ 4 hours =5:00pm
 
Hope this helps---ptaylor
 
 
  | 
 
  
 
 |   
 
 |   
 |  |