Question 846164: It takes an electrician 45 minutes to wire an office in a new office building that is being built. The electrician signed a contract to wire all offices on 6 floors of the new building. There are 50 offices on each floor. How many weeks should the electrician allow for this job if he works a standard work week(8 hours a day 5 days a week)? Express the answer in decimal form rounded to the tenths place Answer by richwmiller(17219) (Show Source):