SOLUTION: If 15 assemblers can complete a certain job in 6 hours, how long will the same job take if the number of assemblers is cut back to 6?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: If 15 assemblers can complete a certain job in 6 hours, how long will the same job take if the number of assemblers is cut back to 6?      Log On


   



Question 844585: If 15 assemblers can complete a certain job in 6 hours, how long will the same job take if the number of assemblers is cut back to 6?
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
15*6=90 worker hours
15 hours for 6 workers