SOLUTION: 6 men can paint a house in 8 days. How long would 4 men take?
Algebra
->
Rate-of-work-word-problems
-> SOLUTION: 6 men can paint a house in 8 days. How long would 4 men take?
Log On
Word Problems: Rate of work, PAINTING, Pool Filling
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Rate-of-work-word-problems
Question 842816
:
6 men can paint a house in 8 days. How long would 4 men take?
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
6*8=48 man days
48/4=12 days for 4 men