SOLUTION: how long will it take 8 workers to complete a job that took 5 workers to complete in 10 days
Algebra
->
Rate-of-work-word-problems
-> SOLUTION: how long will it take 8 workers to complete a job that took 5 workers to complete in 10 days
Log On
Word Problems: Rate of work, PAINTING, Pool Filling
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Rate-of-work-word-problems
Question 842705
:
how long will it take 8 workers to complete a job that took 5 workers to complete in 10 days
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
5 workers in 10 days is 5*10=50 worker days
50/8=6.25 days to complete the job.