SOLUTION: ) P&Q can harvest a field in 5 & 7 days respectively. After p has worked for 3 days , he is joined by Q. in how many more days will the work be completed?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: ) P&Q can harvest a field in 5 & 7 days respectively. After p has worked for 3 days , he is joined by Q. in how many more days will the work be completed?
Log On
Question 839212: ) P&Q can harvest a field in 5 & 7 days respectively. After p has worked for 3 days , he is joined by Q. in how many more days will the work be completed? Answer by ankor@dixie-net.com(22740) (Show Source):
You can put this solution on YOUR website! P&Q can harvest a field in 5 & 7 days respectively.
After p has worked for 3 days , he is joined by Q.
in how many more days will the work be completed?
:
Let t = time to complete the job. (also time worked by Q)
then
(t+3) = time worked by P
:
Let the completed job = 1
:
Each will do a fraction of the job, the two fractions add up to 1
: + = 1
multiply equation by 35, cancel the denominators.
7(t+3) + 5t = 35
7t + 21 + 5t= 35
7t + 5t = 35 - 21
12t = 14
t = 14/12
t = 1 days to complete the job
:
:
Check on calc (P works 4 days) + =
.834 + .166 = 1