Question 836172: Jim and Frank can finish a job in 6 days.
Tim and Jim can finish a job in 7.5 days.
Tim and Frank can finish a job in 10 days.
If they work alone, how long will it take each one to complete the job? Answer by richwmiller(17219) (Show Source):
You can put this solution on YOUR website! 1/j+1/f=1/6,
1/t+1/j=1/7.5,
1/t+1/f=1/10
f = 15, j = 10, t = 30
check
1/10+1/15=1/6
3/30+2/30=1/6
5/30=1/6
ok
1/10+1/30=1/7.5
3/30+1/30=1/7.5
4/30=1/7.5
ok
1/30+1/15=1/10
1/30+2/30=1/10
3/30=1/10
ok