SOLUTION: if 5 men complete work in 100 days than how many men complete the same work in 20 days ?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: if 5 men complete work in 100 days than how many men complete the same work in 20 days ?       Log On


   



Question 833823: if 5 men complete work in 100 days than how many men complete the same work in 20 days ?

Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
5*100= 500 man days
500/20=25 men needed to do 500 man days in 20 days