SOLUTION: 10 people finish a job in 16 hours, how many hours would it take for 8 people to finish the same job, working at the same pace
Algebra ->
Proportions
-> SOLUTION: 10 people finish a job in 16 hours, how many hours would it take for 8 people to finish the same job, working at the same pace
Log On
Question 831680: 10 people finish a job in 16 hours, how many hours would it take for 8 people to finish the same job, working at the same pace Found 2 solutions by hovuquocan1997, edjones:Answer by hovuquocan1997(83) (Show Source):
You can put this solution on YOUR website! = man-hour for 10 people
Now you only have 8 people, to find the time =
TA-DAH
You need 20 hours for 8 people to finish the job :D