Question 830908: Q. 12 employees complete a work in 20 days.Same work 8 employee complete work how much days
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
12*20=240 man days
240/8=30 days for 8 men to complete the same job