Q. 12 employees complete a work in 20 days.Same work 8 employee complete work how much days
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
12*20=240 man days
240/8=30 days for 8 men to complete the same job