Question 829444: If 6men take 5 days to complete a job.how long would the same job take 15 men?
Could you answer this without using algebra would be good.
You can put this solution on YOUR website! Basic Algebra is just logical thinking, everyone should be able to do it.
:
If 6men take 5 days to complete a job.how long would the same job take 15 men?
:
Find how many man-days required to complete the job.
6*5 = 30 man-days
:
Find how many days for 15 men to do the same job
30/15 = 2 days
:
Check this by finding the the man-days again
15 * 2 = 30 man-days, which we agreed would complete the job