You can put this solution on YOUR website! Men______________Days for 1 job
6________________15
1________________15*6, because each man is assumed to have the same rate as another man. One man needs 6 times more time than 6 men.
The one-man rate of work is 1 job per 90 days.
R rate in jobs per day
t time in days
j The quantity of job or jobs
Question about t when 10 men instead of 1 man:
90 days.