Question 826018: If it takes 64 men 15 days to complete a job, how many more men would be required to complete the work in 12 days? Found 2 solutions by Alan3354, richwmiller:Answer by Alan3354(69443) (Show Source):
You can put this solution on YOUR website! If it takes 64 men 15 days to complete a job, how many more men would be required to complete the work in 12 days?
--------------
64*15 = men*12