Question 819828: A manager needs a team of 20 staff members to finish a project in 12 days. How many staff will be needed to finish a project in 6 days?
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
20*12=240 staff days
240/6=40 members to finish in 6 days if they don't get in each others way