SOLUTION: A manager needs a team of 20 staff members to finish a project in 12 days. How many staff will be needed to finish a project in 6 days?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A manager needs a team of 20 staff members to finish a project in 12 days. How many staff will be needed to finish a project in 6 days?
Log On
Question 819828: A manager needs a team of 20 staff members to finish a project in 12 days. How many staff will be needed to finish a project in 6 days? Answer by richwmiller(17219) (Show Source):
You can put this solution on YOUR website! 20*12=240 staff days
240/6=40 members to finish in 6 days if they don't get in each others way