Question 815323: X can do 3/4 of a work in 12 days, he ca finish the 1/2 work in:..........................?
Answer by ewatrrr(24785) About Me  (Show Source):
You can put this solution on YOUR website!
 
Hi,
X can do 3/4 of a work in 12 days, he can finish the 1/2 work in "d" days.
%283%2F4%29%2F12+=+%281%2F2%29%2Fd |Cross Multiplying to solve
%283%2F4%29d+=+6
d = 8 days