SOLUTION: if 9 men can do a work for 5 hrs a day in 16 days, in how many days will 18 men can do the work working 5 hrs
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: if 9 men can do a work for 5 hrs a day in 16 days, in how many days will 18 men can do the work working 5 hrs
Log On
Question 813537: if 9 men can do a work for 5 hrs a day in 16 days, in how many days will 18 men can do the work working 5 hrs Found 2 solutions by josmiceli, josgarithmetic:Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! Keep everything in terms of hours hrs
The rate of working of 9 men is:
( 1 job ) / ( 80 hrs )
---------------
Twice as many men can do the same
job in half the time, so
18 men can do 1 job in hrs
If they work 5 hrs a day,
------------
18 men can do the job in 8 days
You can put this solution on YOUR website! First look at the one man rate per hour.
9 men for 5*16 hours_____________________1 man for 9*5*16 hours because one man must work 9 times longer. jobs per hour.
Now, 18 men work at the rate of jobs per hour.
FIVE hours?
How much of the job? jobs. This is job. That is for 1 day, 5 hours per day.
Using that rate as (1/8) job per day, how many days for 1 whole job?
Let d = number of days. or 8 days.