SOLUTION: Ten Painter Working 8 Hours Daily take 15 Days To paint 3 Houses Of 4 Rooms Each. How many Painters Working 6 Hours Daily for 25 Days will be Required To paint 12 houses Of 3 Rooms
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: Ten Painter Working 8 Hours Daily take 15 Days To paint 3 Houses Of 4 Rooms Each. How many Painters Working 6 Hours Daily for 25 Days will be Required To paint 12 houses Of 3 Rooms
Log On
Question 800602: Ten Painter Working 8 Hours Daily take 15 Days To paint 3 Houses Of 4 Rooms Each. How many Painters Working 6 Hours Daily for 25 Days will be Required To paint 12 houses Of 3 Rooms Each? Answer by ankor@dixie-net.com(22740) (Show Source):
You can put this solution on YOUR website! Ten Painter Working 8 Hours Daily take 15 Days To paint 3 Houses Of 4 Rooms Each.
Find how many man-hours per room = 100 man-hrs per room
:
How many Painters Working 6 Hours Daily for 25 Days will be Required To paint 12 houses Of 3 Rooms Each?
let m = no. of men required to accomplish this
m*6*25 = 12*3*100
150m = 3600
m = 3600/150
m = 24 men required