Question 796340
:
Nine cooks take 4 hours to prepare a school lunch. How long would 6 cooks take to prepare the lunch?
Answer by
solver91311(24713)
(
Show Source
):
You can
put this solution on YOUR website!
If 9 cooks take 4 hours to prepare 1 lunch,
Then 9 cooks take 1 hour to prepare
of a lunch.
Then 1 cook takes 1 hour to prepare
of a lunch
Then 6 cooks take 1 hour to prepare
of a lunch
Then 6 cooks take 6 hours to prepare 1 lunch.