SOLUTION: It takes 3 people 20 days to finish a job. How long will it take 4 people working at the same pace in a 6 day work week?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: It takes 3 people 20 days to finish a job. How long will it take 4 people working at the same pace in a 6 day work week?      Log On


   



Question 784845: It takes 3 people 20 days to finish a job. How long will it take 4 people working at the same pace in a 6 day work week?
Answer by stanbon(75887) About Me  (Show Source):
You can put this solution on YOUR website!
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the same pace in a 6 day work week?
------
# of days and # of people are inversely related::
d = k/p
-------
Solve for "k" using "It takes 3 people 20 days to finish a job".
-------
20 = k/3
k = 60
-------
Equation:
d = 60/p
---------
How long will it take 4 people working at the same pace in a 6 day work week?
d = 60/4
# of days = 15
=================
Cheers,